[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931578":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931578,603,1,"单选题","在双代号网络计划中，当计划工期等于计算工期时，关键线路上的工作一定是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","总时差大于自由时差",false,{"key":16,"text":17,"correct":14},"B","最早开始时间小于等于最迟开始时间",{"key":19,"text":20,"correct":21},"C","最早完成时间等于最迟完成时间",true,{"key":23,"text":24,"correct":14},"D","相邻工作之间时间间隔大于零","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]