[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931577":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":9},931577,603,2,"多选题","",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","第4天至第5天的实际进度为匀速进展",false,{"key":16,"text":17,"correct":18},"B","第3天至第6天的计划进度为匀速进展",true,{"key":20,"text":21,"correct":14},"C","实施过程中实际停工累计0.5天",{"key":23,"text":24,"correct":14},"D","第4天实际工作量与计划工作量相同",{"key":26,"text":27,"correct":18},"E","第8天结束时该工作已按计划完成","BE",{"id":6,"name":30,"category":31,"favorite":32},"质量、投资、进度控制","建筑工程",0]