[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931575":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931575,603,2,"多选题","能够便于统计完成计划各个时间分布中所需资源的网络计划有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","横道图",true,{"key":16,"text":17,"correct":18},"B","双代号网络图",false,{"key":20,"text":21,"correct":18},"C","单代号网络图",{"key":23,"text":24,"correct":18},"D","单代号搭接网络图",{"key":26,"text":27,"correct":14},"E","双代号时标网路图","AE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]