[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931574":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931574,603,1,"单选题","当监理工程师接受建设单位的委托对建设工程实施全过程监理时，为了有效地控制建设工程进度，监理工程师最早应在( )阶段协助建设前段时间确定工期总目标。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","前期决策",false,{"key":16,"text":17,"correct":18},"B","设计前准备",true,{"key":20,"text":21,"correct":14},"C","建设准备",{"key":23,"text":24,"correct":14},"D","施工准备","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]