[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931573":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931573,603,2,"多选题","建设工程的静态投资部分包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","基本预备费",true,{"key":16,"text":17,"correct":18},"B","涨价预备费",false,{"key":20,"text":21,"correct":14},"C","建筑安装工程费",{"key":23,"text":24,"correct":18},"D","铺底流动资金",{"key":26,"text":27,"correct":14},"E","工程建设其他费","ACE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]