[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931570":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931570,603,1,"单选题","下列关于FIDIC施工合同约定的工程计量程序的描述中错误的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包商应及时亲自或另派合格代表，协助工程师进行测量",false,{"key":16,"text":17,"correct":14},"B","承包商应提供工程师要求的任何具体材料",{"key":19,"text":20,"correct":21},"C","承包商必须在工程师的测量记录上签字予以确认",true,{"key":23,"text":24,"correct":14},"D","承包商如果未能到测量现场，则工程师的测量视为被认可","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]