[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931569":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931569,603,1,"单选题","在设备工程设计进度管理中，编制技术任务书、确定设备的基本参数及主要技术性能指标等技术文件的完成日期是设备工程( )进度管理目标。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计准备",false,{"key":16,"text":17,"correct":18},"B","初步设计",true,{"key":20,"text":21,"correct":14},"C","技术设计",{"key":23,"text":24,"correct":14},"D","工作图设计","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]