[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931563":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931563,603,2,"多选题","在工期固定--资源均衡优化中，关于调整过程的描述，正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","压缩关键工作的持续时间",false,{"key":16,"text":17,"correct":18},"B","调整非关键工作的开始时间",true,{"key":20,"text":21,"correct":14},"C","改变关键工作的逻辑关系",{"key":23,"text":24,"correct":14},"D","减少工作的资源强度",{"key":26,"text":27,"correct":18},"E","关键工作的开始时间保持不变","BE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]