[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931556":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931556,603,2,"多选题","下列选项中，属于设备制造过程投资管理措施的有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","编制资金使用计划",true,{"key":16,"text":17,"correct":14},"B","处理合同变更，确定变更价款",{"key":19,"text":20,"correct":21},"C","处理设备安装过程中的索赔，确定索赔价款",false,{"key":23,"text":24,"correct":14},"D","审核并签发付款证书，办理结算",{"key":26,"text":27,"correct":21},"E","处理设备运输损耗","ABD","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]