[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931555":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931555,603,2,"多选题","关于双代号网络图的组成，下列描述正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","节点表示工作间的逻辑关系，箭线表示工作及其进行的方向",false,{"key":16,"text":17,"correct":18},"B","节点表示工作的开始或结束，箭线表示工作及其进行的方向",true,{"key":20,"text":21,"correct":14},"C","节点表示工作，箭线表示工作间的逻辑关系",{"key":23,"text":24,"correct":14},"D","节点表示工作，箭线表示工作及其进行的方向",{"key":26,"text":27,"correct":18},"E","箭线表示工作及其进行的方向，箭尾节点代号小于箭头节点代号","BE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]