[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931550":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931550,603,1,"单选题","在某工程网络计划中，工作M的最早开始时间和最迟开始时间分别为第15天和第18天，其持续时间为7天。工作M有2项紧后工作，它们的最早开始时间分别为第24天和第26天，则工作M的总时差和自由时差( )天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分别为4和3；",false,{"key":16,"text":17,"correct":14},"B","均为3；",{"key":19,"text":20,"correct":21},"C","分别为3和2；",true,{"key":23,"text":24,"correct":14},"D","均为2；","总时差18-15=3；自由时差24-15-7=2",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]