[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931549":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":9},931549,603,2,"多选题","",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","到第3月末，实际进度正常",true,{"key":16,"text":17,"correct":18},"B","第4月内实际进展超前",false,{"key":20,"text":21,"correct":14},"C","第2月前半月本工作停工",{"key":23,"text":24,"correct":18},"D","第3月至第5月实际进度为非匀速",{"key":26,"text":27,"correct":18},"E","预计本工作能够按时完成","AC",{"id":6,"name":30,"category":31,"favorite":32},"质量、投资、进度控制","建筑工程",0]