[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931548":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931548,603,1,"单选题","工程双代号网络计划中，某项工作的最早完成时间是指其( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","最迟完成时间与工作自由时差之差；",false,{"key":16,"text":17,"correct":14},"B","最早开始时间与工作自由时差之和；",{"key":19,"text":20,"correct":21},"C","最迟完成时间与工作总时差之差；",true,{"key":23,"text":24,"correct":14},"D","最早开始时间与工作总时差之和。","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]