[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931545":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931545,603,1,"单选题","某设备安装工程9月份拟完工程计划支出8万元，已完工程计划支出5万元，已完工程实际支出10万元，则该设备安装工程9月份的费用绝对偏差和相对偏差分别为( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2万元；40％",false,{"key":16,"text":17,"correct":14},"B","3万元：60％",{"key":19,"text":20,"correct":21},"C","5万元；100％",true,{"key":23,"text":24,"correct":14},"D","-3万元；-37.5％","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]