[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931541":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931541,603,2,"多选题","在工程网络计划中，当计划工期等于计算工期时，关键工作的判定( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","该工作的总时差为零",true,{"key":16,"text":17,"correct":18},"B","该工作与其紧后工作之间的时间间隔为零",false,{"key":20,"text":21,"correct":14},"C","该工作的最早开始时间与最迟开始时间相等",{"key":23,"text":24,"correct":18},"D","该工作的自由时差最小",{"key":26,"text":27,"correct":18},"E","该工作的持续时间最长","AC","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]