[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931529":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931529,603,2,"多选题","在下列实际进度与计划进度的比较方法中，既可以从局部又可以从整体角度反映设备工程实际进度进展情况的有( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","横道图比较法",false,{"key":16,"text":17,"correct":14},"B","S形曲线比较法",{"key":19,"text":20,"correct":14},"C","前锋线比较法",{"key":22,"text":23,"correct":24},"D","“香蕉”曲线比较法",true,{"key":26,"text":27,"correct":24},"E","横道图与“香蕉”曲线综合比较法","DE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]