[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931525":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931525,603,1,"单选题","工期固定一资源均衡优化是在网络计划工期不变的条件下，通过调整网络计划中( )，使资源消耗尽可能达到均衡。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作间的逻辑关系",false,{"key":16,"text":17,"correct":18},"B","非关键工作的开始时间",true,{"key":20,"text":21,"correct":14},"C","非关键工作的持续时间",{"key":23,"text":24,"correct":14},"D","资源的需求总量","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]