[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931521":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},931521,603,1,"单选题","当实际施工进度发生拖延时，为加快施工进度而采取的组织措施可以是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","重新划分施工段，增加工作面",true,{"key":16,"text":17,"correct":18},"B","采用先进施工方法，减少施工过程的数量",false,{"key":20,"text":21,"correct":18},"C","明确计划任务，实行包干奖励",{"key":23,"text":24,"correct":18},"D","改进施工工艺，缩短工艺技术间歇时间","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]