[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931520":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931520,603,1,"单选题","工作和工作之间的逻辑关系都不确定，且工作持续时间也不确定，而按随机变量进行分析的网络计划技术是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","关键线路法",false,{"key":16,"text":17,"correct":14},"B","计划评审技术",{"key":19,"text":20,"correct":21},"C","图示评审技术",true,{"key":23,"text":24,"correct":14},"D","风险评审技术","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]