[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931517":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},931517,603,1,"单选题","在单代号网络计划中，某工作与其仅有的四项紧后工作的时间间隔分别是6天、3天、1天和4天，则该工作的自由时差是( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",true,{"key":16,"text":17,"correct":18},"B","3",false,{"key":20,"text":21,"correct":18},"C","4",{"key":23,"text":24,"correct":18},"D","6","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]