[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931514":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":9},931514,603,2,"多选题","",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作2-4的总时差为0",true,{"key":16,"text":17,"correct":18},"B","工作6-7为关键工作",false,{"key":20,"text":21,"correct":18},"C","工作3-6的自由时差为3",{"key":23,"text":24,"correct":14},"D","工作2-5的自由时差为2",{"key":26,"text":27,"correct":14},"E","工作1-3的自由时差为0","ADE",{"id":6,"name":30,"category":31,"favorite":32},"质量、投资、进度控制","建筑工程",0]