[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931511":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931511,603,1,"单选题","在设计工作中，由于监理工程师未能及时将业主对电梯选型的改变传达到设计单位而影响到设计进度的情况属于( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设意图和要求改变的影响",false,{"key":16,"text":17,"correct":18},"B","设计协调配合的影响",true,{"key":20,"text":21,"correct":14},"C","工程变更的影响",{"key":23,"text":24,"correct":14},"D","材料代用、设备选用失误的影响","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]