[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931510":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931510,603,1,"单选题","在单代号网络计划中，某工作D有四项紧后工作 H、L、M和N，此四项紧后工作的总时差分别是2天、3天、6天和1天，工作D与 H、L、M和N工作的时间间隔分别是4天、2天、1天和3天，则工作D的总时差是( )天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":21},"C","4",true,{"key":23,"text":24,"correct":14},"D","5","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]