[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931509":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931509,603,2,"多选题","网络计划“资源有限一工期最短”的优化方法是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","占用相关工作的自由时差",true,{"key":16,"text":17,"correct":18},"B","占用所有工作的自由时差",false,{"key":20,"text":21,"correct":14},"C","后移使工期延长时间最短的工作",{"key":23,"text":24,"correct":18},"D","占用所有工作的总时差",{"key":26,"text":27,"correct":18},"E","后移使工期延长时间最长的工作","AC","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]