[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931504":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931504,603,2,"多选题","在工程双代号网络计划中，某项工作的最早完成时间是指其( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","开始节点的最早时间与工作部时差之和",false,{"key":16,"text":17,"correct":18},"B","开始节点的最早时间与工作持续时间之和",true,{"key":20,"text":21,"correct":14},"C","完成节点的最迟时间与工作持续时间之差",{"key":23,"text":24,"correct":18},"D","完成节点最迟时间与工作总时差之差",{"key":26,"text":27,"correct":14},"E","完成节点的最迟时间与工作自由时差之差","BD","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]