[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931502":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},931502,603,1,"单选题","在工程网络计划执行过程中，如果某项非关键工作实际进度拖延的时间超过其总时差，则( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","网络计划的计算工期不会改变",false,{"key":16,"text":17,"correct":14},"B","该工作的总时差不变",{"key":19,"text":20,"correct":14},"C","该工作的自由时差不变",{"key":22,"text":23,"correct":24},"D","网络计划中关键线路改变",true,"",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]