[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931496":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},931496,603,1,"单选题","在建设工程施工阶段，监理工程师进度控制的工作内容包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","审查承包商调整后的施工进度计划",true,{"key":16,"text":17,"correct":18},"B","编制施工总进度计划和单位工程施工进度计划",false,{"key":20,"text":21,"correct":18},"C","协助承包商确定工程延期时间和实施进度计划",{"key":23,"text":24,"correct":18},"D","按时提供施工场地并适时下达开工令","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]