[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931493":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931493,603,1,"单选题","在双代号时标网络计划中，当某项工作之后紧接实工作时，该工作箭线右边一段的波形线表示( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工作间的逻辑关系",false,{"key":16,"text":17,"correct":14},"B","工作的总时差",{"key":19,"text":20,"correct":21},"C","工作的自由时差",true,{"key":23,"text":24,"correct":14},"D","工作的持续时间","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]