[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931488":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931488,603,2,"多选题","对于独立的常规投资项目，下列描述中正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","财务净现值随折现率的增大而增大",false,{"key":16,"text":17,"correct":18},"B","财务内部收益率是财务净现值等于零时的折现率",true,{"key":20,"text":21,"correct":18},"C","财务内部收益率与财务净现值的评价结论是一致的。",{"key":23,"text":24,"correct":14},"D","在某些情况下存在多个财务内部收益率",{"key":26,"text":27,"correct":18},"E","财务内部收益率考虑了项目在整个计算期的经济状况。","BCE","财务净现值随折现率的增大而减小。对于非常规投资项目，存在多个财务内部收益率",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]