[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931487":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931487,603,1,"单选题","由实施组织根据组织原则和资源优化配置原则决定工作间的先后顺序称为( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","逻辑关系",false,{"key":16,"text":17,"correct":14},"B","工艺关系",{"key":19,"text":20,"correct":21},"C","组织关系",true,{"key":23,"text":24,"correct":14},"D","工作关系","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]