[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931480":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931480,603,2,"多选题","当利用S形曲线比较法时，通过比较计划S形曲线和实际S形曲线，可以获得的信息有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程项目实际进度比计划进度超前或拖后的时间；",true,{"key":16,"text":17,"correct":18},"B","工程项目中各项工作实际完成的任务量；",false,{"key":20,"text":21,"correct":14},"C","工程项目实际进度比计划进度超额完成或拖欠的任务量；",{"key":23,"text":24,"correct":18},"D","工程项目中各项工作实际进度比计划进度超前或拖后的时间；",{"key":26,"text":27,"correct":14},"E","预测后期工程进度。","ACE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]