[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931479":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},931479,603,1,"单选题","某项目检查期间的挣值为100万元，计划价值为120万元，实际成本为90万元。下列关于偏差计算的说法，正确的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","进度偏差(SV)为-20万元，表示进度提前",false,{"key":16,"text":17,"correct":14},"B","进度偏差(SV)为-30万元，表示进度延误",{"key":19,"text":20,"correct":14},"C","成本偏差(CV)为-30万元，表示实际成本超过预算",{"key":22,"text":23,"correct":24},"D","成本偏差(CV)为10万元，表示实际成本低于预算",true,"",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]