[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931478":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931478,603,2,"多选题","某工作的最早开始时间是第3天，最晚开始时间是第13天，最早完成时间是第9天，最晚完成时间是第19天，则该任务( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","在关键路径上",false,{"key":16,"text":17,"correct":18},"B","不在关键路径上",true,{"key":20,"text":21,"correct":14},"C","进展情况良好",{"key":23,"text":24,"correct":18},"D","工期为6天",{"key":26,"text":27,"correct":14},"E","工期为10天","BD","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]