[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931476":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931476,603,2,"多选题","下列说法正确的有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程变更须由原设计单位提供变更后的图纸和说明",true,{"key":16,"text":17,"correct":14},"B","承包人不得自行对原设计进行变更",{"key":19,"text":20,"correct":21},"C","工程师采用承包人合理的变更建议，其收益归承包人",false,{"key":23,"text":24,"correct":14},"D","发包人需要对工程设计变更，应不迟于变更前14天以书面形式通知承包人",{"key":26,"text":27,"correct":21},"E","工程变更须经工程师提供变更后的说明","ABD","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]