[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931469":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931469,603,2,"多选题","采用不平衡报价时，通常可以( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","对能早期得到结算付款的分部分项工程的单价定得较低，对后期的施工分项单价可以适当提高",false,{"key":16,"text":17,"correct":14},"B","估计施工中工程量可能会增加的项目，单价可以降低，工程量会减少的项目单价可以提高",{"key":19,"text":20,"correct":21},"C","设计图纸不明确或有错误的，估计今后修改后工程量会增加的项目，单价提高，工程内容说明不清的，单价降低",true,{"key":23,"text":24,"correct":21},"D","对于暂列数额(或工程)，预计做的可能性较大，价格可定高些，估计不一定发生的则单价低些",{"key":26,"text":27,"correct":21},"E","零星用工报价高于一般分部分项工程中的工资单价","CDE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]