[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931468":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931468,603,2,"多选题","",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","总工期为20天",false,{"key":16,"text":17,"correct":18},"B","关键线路有1条",true,{"key":20,"text":21,"correct":14},"C","关键线路有2条",{"key":23,"text":24,"correct":18},"D","工作H的总时差为1天",{"key":26,"text":27,"correct":18},"E","工作D的自由时差为3天","BDE","经计算，各工作的ES\u002FEF\u002FLS\u002FLF\u002FTF\u002FFF参数如下：工作A：0\u002F2\u002F0\u002F2\u002F0\u002F0工作B：2\u002F7\u002F2\u002F7\u002F0\u002F0工作C：2\u002F6\u002F5\u002F9\u002F3\u002F3工作D：7\u002F9\u002F10\u002F12\u002F3\u002F3工作E：9\u002F12\u002F9\u002F12\u002F0\u002F0工作F：7\u002F9\u002F7\u002F9\u002F0\u002F0工作G：12\u002F18\u002F12\u002F18\u002F0\u002F0工作H：12\u002F17\u002F13\u002F18\u002F1\u002F1工作I：18\u002F21\u002F18\u002F21\u002F0\u002F0所以，总工期为21天，关键线路有1条：ABFEGI，工作H的总时差为1天，工作D的自由时差为3天。",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]