[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931464":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931464,603,2,"多选题","遇到( )情况时，承包商可以向业主要求既延长工期，又索赔费用。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","设计文件有缺陷",true,{"key":16,"text":17,"correct":14},"B","由于业主原因造成临时停工",{"key":19,"text":20,"correct":14},"C","业主供应的设备和材料推迟到货",{"key":22,"text":23,"correct":24},"D","特殊恶劣气候，造成施工停顿",false,{"key":26,"text":27,"correct":14},"E","工程师对竣工试验干扰","ABCE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]