[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931456":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},931456,603,1,"单选题","网络计划的优化中工期优化的目的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","压缩计算工期；",true,{"key":16,"text":17,"correct":18},"B","压缩要求工期；",false,{"key":20,"text":21,"correct":18},"C","压缩计划工期；",{"key":23,"text":24,"correct":18},"D","压缩实际工期；","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]