[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931444":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931444,603,1,"单选题","挣值(EV)-计划价值(PV)＞0，表明( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","成本节约",false,{"key":16,"text":17,"correct":14},"B","成本超支",{"key":19,"text":20,"correct":21},"C","进度提前",true,{"key":23,"text":24,"correct":14},"D","进度延误","进度偏差(ScheduleVariance，SV)进度偏差是指检查日期的挣值(EV)与计划价值(PV)之间的差异，可用来表明项目是否落后于基准进度。计算公式为：SV=EV-PV当SV＞O时表示进度提前，SV＜O时表示进度延误。若SV=O，表明进度按计划执行。当项目完工时，全部计划价值都将实现，挣值等于计划价值，因此EVM进度偏差最终将等于零。",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]