[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931443":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931443,603,1,"单选题","某设备工程采用总承包(EP C)模式发包，在设备采购进度管理中，应由设备监理工程师审核的文件是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设备采购招标文件",false,{"key":16,"text":17,"correct":14},"B","设备采购评标报告",{"key":19,"text":20,"correct":21},"C","设备采购进度计划",true,{"key":23,"text":24,"correct":14},"D","中标供应商名单","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]