[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931435":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931435,603,1,"单选题","依据《建设工程工程量清单计价规范》中的规定，由于设计变更引起新的工程量清单项目，其相应综合单价应( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由承包商自行确定",false,{"key":16,"text":17,"correct":18},"B","由承包商提出，经发包人确认后，作为结算依据",true,{"key":20,"text":21,"correct":14},"C","由发包人自行确定",{"key":23,"text":24,"correct":14},"D","由监理工程师提出，经发包人确认后，作为结算依据","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]