[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931419":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},931419,603,1,"单选题","在修堤坝时，一定要等土堤自然沉降后才能修护坡，筑土堤与修护坡之间的等待时间差值称为( )搭接关系。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","FTS",true,{"key":16,"text":17,"correct":18},"B","STS",false,{"key":20,"text":21,"correct":18},"C","FTF",{"key":23,"text":24,"correct":18},"D","STF","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]