[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931416":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931416,603,2,"多选题","进度计划执行的监测与调整阶段，设备监理工程师的主要工作内容包括( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","进度调整",true,{"key":16,"text":17,"correct":14},"B","进度数据采集",{"key":19,"text":20,"correct":14},"C","进度偏差分析",{"key":22,"text":23,"correct":24},"D","处理设备工程的索赔事宜",false,{"key":26,"text":27,"correct":24},"E","核实已完成任务量，签发应付工程进度款","ABC","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]