[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931415":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931415,603,1,"单选题","建设工程组织流水施工时，其特点之一是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","由一个专业队在各施工段上依次施工",false,{"key":16,"text":17,"correct":14},"B","同一时间段只能有一个专业队投入流水施工",{"key":19,"text":20,"correct":21},"C","各专业队按施工顺序应连续、均衡地组织施工",true,{"key":23,"text":24,"correct":14},"D","施工现场的组织管理简单，工期最短","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]