[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931410":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},931410,603,1,"单选题","在某工程网络计划中，已知工作M的总时差和自由时差分别为7天和4天，监理工程师检查实际进度时发现该工作的持续时间延长了3天，说明此时工作M的实际进度( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","既不影响总工期，也不影响其后续工作的正常进行；",true,{"key":16,"text":17,"correct":18},"B","不影响总工期，但将其后续工作的开始时间推迟3天；",false,{"key":20,"text":21,"correct":18},"C","将使总工期延长3天，但不影响其后续工作的正常进行；",{"key":23,"text":24,"correct":18},"D","将其后续工作的开始时间推迟3天，并使总工期延长3天；","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]