[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931394":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931394,603,2,"多选题","下列关于静态投资回收期的说法，正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","计算静态投资回收期时不考虑资金的时间价值",true,{"key":16,"text":17,"correct":18},"B","当静态投资回收期小于项目寿命期时，可接受该项目",false,{"key":20,"text":21,"correct":14},"C","当静态投资回收期大于基准投资回收期时，应拒绝该项目",{"key":23,"text":24,"correct":18},"D","静态投资回收期即为累计净现金流量开始出现正值的年份数",{"key":26,"text":27,"correct":18},"E","静态投资回收期肯定大于动态投资回收期","AC","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]