[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931368":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931368,603,2,"多选题","已知网络计划中某工作只有一项紧后工作，该紧后工作的最早开始时间为第9天，本工作的最早开始时间和最迟开始时间分别为第4天和第10天。如果本工作的持续时间为3天，则其( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","总时差为6天",true,{"key":16,"text":17,"correct":18},"B","自由时差为1天",false,{"key":20,"text":21,"correct":14},"C","自由时差为2天",{"key":23,"text":24,"correct":18},"D","与紧后工作之间的时间间隔为1天",{"key":26,"text":27,"correct":18},"E","总时差为5天","AC","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]