[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931361":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931361,603,1,"单选题","监理工程师对施工进度控制的工作细则中所包括的内容有( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","明确划分施工段的要求",false,{"key":16,"text":17,"correct":14},"B","工程进度款支付的时间与方式",{"key":19,"text":20,"correct":21},"C","进度检查的周期与进度报表的格式",true,{"key":23,"text":24,"correct":14},"D","材料进场的时间与检验方式","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]