[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931358":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931358,603,2,"多选题","项目技术经济分析中往往用利率作为衡量资金时间价值的相对尺度，其组成部分包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","对时间因素补偿",true,{"key":16,"text":17,"correct":18},"B","对空间因素的补偿",false,{"key":20,"text":21,"correct":18},"C","对环境因素的补偿",{"key":23,"text":24,"correct":14},"D","对风险因素的补偿",{"key":26,"text":27,"correct":14},"E","对通货膨胀因素的补偿","ADE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]