[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931356":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931356,603,1,"单选题","关键路径是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","是项目中具有最高技术风险的最早的一系列事件和活动",false,{"key":16,"text":17,"correct":14},"B","是项目中具有最高成本的一系列事件和活动",{"key":19,"text":20,"correct":21},"C","如果按现有网络计划执行的话，是从现在到项目结束过程中具有最长链的一系列事件和活动",true,{"key":23,"text":24,"correct":14},"D","是一个有趣的概念，对于项目经理来说影响不大","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]